Question 3 3 pts The Green Machine Manufacturing Company has
Question 3 3 pts The Green Machine Manufacturing Company has the option to make or buy a component part for one of its lawnmowers. The annual requirement is 25,000 units. A supplier is able to supply the parts for $12.25 per piece. Green Machine estimates that it will cost $700 to prepare the contract with the supplier. To make the parts in-house, Green Machine must invest S100,000 in capital equipment. They estimate it will cost $9.00 per piece to produce the part in-house. Carry all calculations out to two decimal places. If the demand is 25,000 units, should Green Machine make or buy the part? Buy the part O Make the part O Both O Neither O Not enough information
Solution
total cost of order for inhouse manufacturing
= 100000 + 25000 *9
= 325000
total cost of order supplied
= 25000 * 12.25 + 700
= 306950
hence buy the part