https://newconnect.mheducation.com/flow/connect.html Saved All of the following are true of lags EXCEPT Click to se They can be any one of four distinct types. They are used to reduce free slack. They are used to more closely represent real situations found in projects They are used to allow work to be accomplished in parallel. ect
Solution
Option D is the correct asnwer.
Lag is the one which indicates the delay in succeesor activity in a given project, and it express its relationship with other activities in the project schedule. So, there is no relation that these lags allow paraller work of all activities in the project. Hence the option D is correct.