ueor 110 TC (a) Compure altenatives A and Rusins the presenn worth method, end denenmine wich alnera you wuald choose

Solution

Project B has highest PW, so project B should be selected

--------------------------------------------------------------------------------------------------------------------------

Year

A

B

C

PV factor @ 10%

PV A

PV B

PV C

0

-210

-110

-160

1

50

70

0

0.90909

45.45454545

63.63636364

0

2

60

70

0

0.82645

49.58677686

57.85123967

0

3

70

70

0

0.75131

52.59203606

52.59203606

0

4

80

70

300

0.68301

54.64107643

47.81094188

204.9040366

Total PV

202.2744348

221.8905812

204.9040366

Initial cost

210

110

160

PW

-7.725565194

111.8905812

44.90403661

--------------------------------------------------------------------------------------------------------------------------

Feel free to comment if you need further assistance J

Pls rate this answer if you found it useful.

Year

A

B

C

PV factor @ 10%

PV A

PV B

PV C

0

-210

-110

-160

1

50

70

0

0.90909

45.45454545

63.63636364

0

2

60

70

0

0.82645

49.58677686

57.85123967

0

3

70

70

0

0.75131

52.59203606

52.59203606

0

4

80

70

300

0.68301

54.64107643

47.81094188

204.9040366

Total PV

202.2744348

221.8905812

204.9040366

Initial cost

210

110

160

PW

-7.725565194

111.8905812

44.90403661

 ueor 110 TC (a) Compure altenatives A and Rusins the presenn worth method, end denenmine wich alnera you wuald choose SolutionProject B has highest PW, so proj
 ueor 110 TC (a) Compure altenatives A and Rusins the presenn worth method, end denenmine wich alnera you wuald choose SolutionProject B has highest PW, so proj
 ueor 110 TC (a) Compure altenatives A and Rusins the presenn worth method, end denenmine wich alnera you wuald choose SolutionProject B has highest PW, so proj