Problem 1 A network consists of the following list Times are

Problem 1:

A network consists of the following list. Times are given in weeks.

a. Draw the network diagram.

b. Which activities form the critical path? Use the longest path method and two-pass method to answer this question.

c. How much slack exists at activities A and F?

d. What is the duration of the critical path?

Note: please show your process of getting the results. Only providing the final answers is not acceptable and will get me a 0%. Thank you in advance.

Sincerly a last semester Grad Student

Activity Preceding Duration
A -- 8
B A 3
C A 17
D A 5
E B 7
F B 8
G C, F 3
H D 2
I H 8
J G, I 6
K E, J 3

Solution

The network precedence diagram as follows :

                                                                                                         A

                                               B

C

D

                    E           

                      F

H

                                                               G

I

                                                                               J

                                                                                                           K

The possible paths and their corresponding durations as follows :

A-B-E- K = 8 +3 +7 + 3 = 21

A-B-F-G-J-K = 8 +3 + 8 +3 +6 +3 = 31

A-C-G-J-K = 8 +17 +3 +6 +3 = 37

A-D-H-I-J-K = 8 +5+2+8+6+3 = 32

Since A-C-G-J-K has the longest , duration it forms the critical path

ACTIVITIES ON CRITICAL PATH = A-C-G-J-K

DURATION OF CRITICAL PATH = 37

Slack of activities B.F = Duration of A-C-G-J-K    - Duration of A-B-F-G-J-K = 37 – 31 = 6 weeks

All activities lying on critical path have ZERO slack. Therefore, Slack for activity A will be ZERO

SLACK OF ACTIVITIES A AND F ARE ZERO AND 6 WEEKS RESPECTIVELY

                                                                                                         A

                                               B

C

D

                    E           

                      F

H

                                                               G

I

                                                                               J

                                                                                                           K

Problem 1: A network consists of the following list. Times are given in weeks. a. Draw the network diagram. b. Which activities form the critical path? Use the
Problem 1: A network consists of the following list. Times are given in weeks. a. Draw the network diagram. b. Which activities form the critical path? Use the

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site