The following jobs are available for processing at time 0 If
The following jobs are available for processing at time 0:
If the Shortest Processing Time rule is used to prioritize work through this work center, and assuming no new jobs arrive while these jobs are being processed, what will be the average job flowtime in this situation?
| Job | Req\'d Process Time (hrs) |
| A | 27 |
| B | 16 |
| C | 19 |
| D | 5 |
| E | 24 |
Solution
As per Shortest processing time the new order is
So we get the following:
Avg Flow time = Completion/ no of tasks
| D | 5 |
| B | 16 |
| C | 19 |
| E | 24 |
| A | 27 |