Homework: Homework 7 Score: 0 of 1 pt 14 of 15 (1 complete) Problem E.9 Professor Mary Beth Marrs took 8 hours to prepare the first lecture in a new course. Traditionally, she has experienced a 90% earning factor. Time spent by Mary to prepare the: 15 lecture hours (round your response to two decimal places) Save HW Score: 5.19%, 0.78 of 15 pts IE Question Help
Solution
Dear Student
Thank you for using Chegg !!
Given that it took 80 labor hrs to install first vending machine.
Learning Rate = 95%
Formula used
T × Ln = Time required for the n th unit
T : - Time required for first unit
L:- Learning Rate
n := no of times T is doubled
n = 2
For the given scenario
Time required for fourth machine installation = 80X 0.95^2
= 72.2 hrs