4670 124 1588 888F FS F3 Solution Occupancy Electrical Days

$4,670 124 $1,588 888F FS F3

Solution

Occupancy Electrical Days cost High Activity 2406 5148 Low activity 124 1588 Change 2282 3560 Variable cost per day: Change in cost/ Change in days 3560 / 2282 = $ 1.56 per day Fixed cost: Total cost 5148 Less: Variable cost 3753 Fixed cost: 1395 Variable cost $ 1.56 per occupancy day Fixed cost $1,395
 $4,670 124 $1,588 888F FS F3 Solution Occupancy Electrical Days cost High Activity 2406 5148 Low activity 124 1588 Change 2282 3560 Variable cost per day: Chan