sorry but the question is in the third picture thank you Che
sorry but the question is in the third picture. thank you
Check my work value 1.00 points 6. What direct labor cost would be included in the company\'s flexible budget for March? Direct labor References eBook &Resources; Learning Objective: 08-02 Prepare a report showing revenue and spending variances Worksheet Learning Objective: 08-04 Compute the direct materials price and quantity variances and explain their significance. Difficulty: 2 Medium Learning Objective: 08-01 Prepare a flexible budget Learning Objective: 08-05 Compute the direct labor rate and efficiency variances and explain their significance Check my workSolution
Solution:
Part 6 --- Labor Cost as per flexible budget for March
Flexible Budget means the budget prepared based on the standard price for actual activity level achieved.
Labor Cost that would be included in the company’s flexible budget for March = Actual Units Produced 26,600 Units x Required Labor Hour per unit 3 hours at standard labor rate $15
= $1,197,000
Part 7 – Direct Labor Efficiency Variance for March = $147,000 Favorable
Labor Quantity / Efficiency Variance
Standard Hours Allowed for actual production:
Actual Production
26600
Units
x Allowed Standard Hours Per Unit
3
Hours
Total Standard Hours Allowed for actual production (SHAP)
79,800
Hours
Actual Labor Hours Worked (AH)
70,000
Hours
Variance or Difference in Hours
9,800
Hours
x Standard Hourly Rate (SHR)
$15.00
per hour
Labor Efficiency Variance
$147,000
Favorable
Part 8 --- Direct Labor Rate Variance for March = $70,000 Unfavorable
Labor Rate Variance
Actual Hourly Rate
$16.00
Per Hour
Standard Hourly Rate
$15.00
Per Hour
Variance or Difference in Rate
$1.00
Per Hour
x Actual Labor Hours worked
70000
Hours
Labor Rate Variance
$70,000
Unfavorable
Part 9 is missing in the question
Part 10 --- Variable Overhead Efficiency Variance for March = $68,600 Favorable
Variable Overhead Efficiency/Quantity Variance
Standard Hours Allowed for actual production:
Actual Production
26,600
Units
x Allowed Standard Hours Per Unit
3
MHs
Total Standard Hours Allowed for actual production (SHAP)
79800
hours
Actual Hours Worked (AH)
70000
Hours
Variance or Difference in Hours
9800
hours
x Standard Hourly Variable Overhead Rate
$7.00
per hour
Variable Overhead Efficiency Variance
$68,600
Favorable
Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you
Pls ask separate question for remaining parts
| Labor Quantity / Efficiency Variance | ||
| Standard Hours Allowed for actual production: | ||
| Actual Production | 26600 | Units |
| x Allowed Standard Hours Per Unit | 3 | Hours |
| Total Standard Hours Allowed for actual production (SHAP) | 79,800 | Hours |
| Actual Labor Hours Worked (AH) | 70,000 | Hours |
| Variance or Difference in Hours | 9,800 | Hours |
| x Standard Hourly Rate (SHR) | $15.00 | per hour |
| Labor Efficiency Variance | $147,000 | Favorable |


