Answer Question 3 Instructions You are preparing a status re
Answer Question 3:
Instructions: You are preparing a status report for your project sponsor and stakeholders and it\'s important to share the project progress using the Earned Value technique. You are preparing your status report for the period ending October 28th. Your project started February 27th. Assume that the project is executed 5 days per week and 8 hours per day with some additional hours that amount to 8 hours every Saturday and Sunday. The project manager\'s table of activities are noted below.
ID
Activity
Original Duration (days)
Actual Duration
(days)
Actual Start Date
Actual Finish Date
%
Complete
Original
Budget
Actual
Budget
10
Site Prep
8
9
2/27
4/26
100
$500,000
$600,000
20
Substructure
12
11
5/1
7/18
100
$1,500,000
$1,350,000
30
Super Substructure
18
-
7/20
-
75
$2,000,000
$1,450,000
40
Exterior
6
-
-
-
0
$400,000
-
50
Interior
14
-
8/31
-
50
$1,800,000
$1,000,000
60
Services
10
-
-
-
0
$1,000,000
-
70
Cleanup
4
-
-
-
0
$200,000
Question 3 - Calculate the BCWP (Earned Value). This is based on the original budget and the actual work completed for the activities that are in progress. This calculation will provide the budgeted cost of the work completed to date.
Activity 30: Super Sub Structure
Original Budget: = $2,000,000
Actual Percent Complete = 75%
Earned Value = 75% * Original Budget _____________________
Activity 50: Interior
Original Budget = $1,800,000
Actual Percent Complete = 50%
Earned Value = 50% * Original Budget ______________________
| ID | Activity | Original Duration (days) | Actual Duration (days) | Actual Start Date | Actual Finish Date | % Complete | Original Budget | Actual Budget |
| 10 | Site Prep | 8 | 9 | 2/27 | 4/26 | 100 | $500,000 | $600,000 |
| 20 | Substructure | 12 | 11 | 5/1 | 7/18 | 100 | $1,500,000 | $1,350,000 |
| 30 | Super Substructure | 18 | - | 7/20 | - | 75 | $2,000,000 | $1,450,000 |
| 40 | Exterior | 6 | - | - | - | 0 | $400,000 | - |
| 50 | Interior | 14 | - | 8/31 | - | 50 | $1,800,000 | $1,000,000 |
| 60 | Services | 10 | - | - | - | 0 | $1,000,000 | - |
| 70 | Cleanup | 4 | - | - | - | 0 | $200,000 |
Solution
Question 3
BCWP = Original budget * %Complete/100
BCWP (Earned Value) = 500000*100/100 + 1500000*100/100 + 2000000*75/100 + 400000*0 + 1800000*50/100 + 1000000*0 + 200000*0
= $ 4,400,000
Activity 30: Super Sub Structure
Original Budget: = $2,000,000
Actual Percent Complete = 75%
Earned Value = 75% * Original Budget = 75%*2000000 = $ 1,500,000
_____________________
Activity 50: Interior
Original Budget = $1,800,000
Actual Percent Complete = 50%
Earned Value = 50% * Original Budget = 50%*1800000 = $ 900,000
_____________________
| ID | Activity | Original | Actual | Actual | Actual | % | Original | Actual | BCWP |
| Duration (days) | Duration (days) | Start Date | Finish Date | Complete | Budget | Budget | Earned Value | ||
| 10 | Site Prep | 8 | 9 | 27-Feb | 26-Apr | 100 | 500,000 | 600,000 | 500,000 |
| 20 | Substructure | 12 | 11 | 1-May | 18-Jul | 100 | 1,500,000 | 1,350,000 | 1,500,000 |
| 30 | Super Substructure | 18 | - | 20-Jul | - | 75 | 2,000,000 | 1,450,000 | 1,500,000 |
| 40 | Exterior | 6 | - | - | - | 0 | 400,000 | - | 0 |
| 50 | Interior | 14 | - | 31-Aug | - | 50 | 1,800,000 | 1,000,000 | 900,000 |
| 60 | Services | 10 | - | - | - | 0 | 1,000,000 | - | 0 |
| 70 | Cleanup | 4 | - | - | - | 0 | 200,000 | 0 |



