What can be the limitations of critical path scheduling Have
What can be the limitations of critical path scheduling? Have a discussion of no less than 50 words.
Solution
Answer:
Limitations of critical path scheduling:
-This scheduling is not suitable for projects that cannot be brolen down into discrete activities with known completion times
-This method is not suitable for working in practical situations as there will be reallocation of projects and activities often
-This method tales too much time to identify all activities and inter relate them .So this scheduling is not suitable for big projects and is complex
-This method is activity based,so it doesnot allow people to track resources independently of the activities
-This is not suitable for projects with lot of overlapping activites
-