Material and Labor Variances Topper Toys has developed a new
Material and Labor Variances
Topper Toys has developed a new toy called the Brainbuster. The company has a standard cost system to help control costs and has established the following standards for the Brainbuster toy:
Direct materials: 8 diodes per toy at $0.30 per diode
Direct labor: 1.2 hours per toy at $7 per hour
During August, the company produced 5,000 Brainbuster toys. Production data on the toy for August follows:
Direct materials: 70,000 diodes were purchased for use in production at a cost of $0.28 per diode. Some 20,000 of these diodes were still in inventory at the end of the month.
Direct labor: 6,400 direct labor-hours were worked at a cost of $48,000.
Required:
1. Compute the following variances for August (and circle whether they are favorable or unfavorable:
a. Direct materials price and quantity variances.
b. Direct labor rate and efficiency variances.
a. Direct Materials Price Variance = __________ favorable or unfavorable
Direct Materials Quantity Variance = __________ favorable or unfavorable
b. Direct Labor Rate Variance = __________ favorable or unfavorable
Direct Labor Efficiency Variance = __________ favorable or unfavorable
Solution
a) Direct material price variance = (0.30-0.28)*70000 = 1400 Favorable
Direct material quantity variance = (5000*8-50000)*0.30 = 3000 Unfavorable
b) Direct labour rate variance = (7*6400-48000) = 3200 Unfavorable
Direct labour efficiency variance = (5000*1.2-6400)*7 = 2800 Unfavorable