The master budget of Crane Company shows that the planned activity level for next year is expected to be 50000 machine hours. At this level of activity, the following manufacturing overhead costs are expected:

$1290000


A flexible budget for a level of activity of 60000 machine hours would show total manufacturing overhead costs of _____?

Indirect labor $680000
Machine supplies 150000
Indirect materials 280000
Depreciation on factory building 180000
Total manufacturing overhead

$1290000

Solution

Total manufacturing overhead costs = {[($680,000 + $150,000 + $280,000) / 50,000] × 60,000} + $180,000 = $1,512,000