5 If machine operating hours are used as the allocation for
5. If machine operating hours are used as the allocation for the following project. A total of $700,000 is allocated to the company for next year. Use the data collected this year to determine the indirect cost rate for each assembly line. Option Indirect cost Estimated Allocated, S Operating Hours 120,000 50,000 175,000 255,000 600 500 1000 I500
Solution
the following is the calculation of indirect cost rate for each assembly line.
| option | indirect cost allocated, $ | estimated operatin hours | indirect cost rate = (cost allocate / hours) |
| 1 | 120,000 | 600 | (120,000/600) =>$200 per hour |
| 2 | 150,000 | 500 | (150,000/500)=>$300 per hour |
| 3 | 175,000 | 1000 | (175,000/1000)=>$175 per hour |
| 4 | 255,000 | 1500 | (255,000/1500)=>$170 per hour |