Question 30 Under the Theory of Constraints which of the fo
Solution
Question 30 & 31
Cycle time is effectively the total time taken by a unit to transverse through the entire production line. It is simply the subtraction of Time of Exit and the Time of Entry. Thus, we can say it basically means the time taken by a production line to produce a unit of goods. There are many variations of this formula-
Research Time- It is the time required by an organization to research upon the various factors of production like type of product to be developed, benchmark activities of production, etc. As Research time involves non-production activities, it is not included in Cycle Time
Idle/Wait Time- It is the time for which a unit stands idle in between two processes. As all processes doesn\'t take the same amount of time, there are high possibility that a batch/unit would have to wait before being acted upon by the next process. As this Idle time involves delay in production, it is included in the cycle time.
Quality Time- The time taken my a production facility to make appropriate Quality Audits and Quality check is called Quality Time. As these quality related activities are a non-production activities, they are not included in cycle time
Root Square Time- This type of methodology is used when the process time is too random and thus, we are required to use the Root mean square values of all cycle times. But in Production line, the cycle times are very constant and thus the variations are very limited, so we are not required to use this methodology.
Set Up Time- It is basically referred to as the time required to make the unit ready for entry into the next process. This would include the time required for any activity to be taken on the units before its entry into a process. Example- If a process requires the iron rods to be rust free, then the time taken to remove the rusts is the Set Up time. As Set up time includes activities important for the production, it in included in the cycle time
Process Time- It is the time taken for the completion of each processes.
Answers- Question 30 --> b) Idle Time Question 31----> a) All of the above
Question 32
Profit is a desired function and hence, we have to maximize it.
Profit after sale of 1 unit of Product A is 50$. Therefore Profit after sale of A units of Product A is 50*A
Profit after sale of 1 unit of Product B is 45$. Therefore Profit after sale of B units of Product B is 45*B
Thus Total Profit would be 50*A+45*B
As our objective is to maximize the total profit, hence the answer is a) Maximize z= 50*A+45*B
