A company should use process costing rather than job order c
A company should use process costing, rather than job order costing, if:
production is only partially completed during the accounting period.
the product is manufactured in batches only as orders are received.
the product is composed of mass-produced homogeneous units.
the product goes through several steps of production.
| a. | production is only partially completed during the accounting period. | |
| b. | the product is manufactured in batches only as orders are received. | |
| c. | the product is composed of mass-produced homogeneous units. | |
| d. | the product goes through several steps of production. |
Solution
Answer ) option c
the product is composed of mass-produced homogeneous units
since job costing is used for customer specifice products
| Answer ) option c the product is composed of mass-produced homogeneous units since job costing is used for customer specifice products |