Calculator The Winston Company estimates that the factory ov
     Calculator The Winston Company estimates that the factory overhead for the following year will be $1,071,90 factory overhead should be machine hours, which is estimated to be 39,700 hours. The total machi overhead for the year were $1,473,000 a. Determine the total factory overhead amount applied. (Round to the nearest dollar.) b. Calculate the over- or underapplied amount for the year. Enter the amount as a positive number c. Prepare the journal entry to close factory overhead into Cost of Goods Sold     
 
  
  Solution
Budgeted OH = $1071900 / 39700 MH = $27 per MH
 
 (a) Applied at $27 X 54900 = 1482300
 (b) Actual Vs Applied = 1473000 – 1482300 = 9300 Overapplied
 (c)
General journal
Debit
Credit
Factory OH
9300
Cost of Goods Sold
9300
| General journal | Debit | Credit | 
| Factory OH | 9300 | |
| Cost of Goods Sold | 9300 | 