You have just been hired by FAB Corporation, the costs.\" You find that the company has never used a flexible budget, and you suggest that preparing such a budget would Cost in $126,400 $ 70,100 $68,400 erences and produced 14,000 units. The company had originally planned to Activity Variances Next >

Solution

Workings

Activity Variance
Static Budget Flexible Budget Activity Variance
Utilities 21800 22220 420 U
Maintenance 60600 62800 2200 U
Supplies 6000 6600 600 U
Indirect Labor 122700 125500 2800 U
Depreciation 68400 68400 0 NONE
Total 279500 285520 6020 U