A product must be ground polished weighed and inspected The

A product must be ground, polished, weighed and inspected. The grinding must precede the polishing and the weighting and the polishing must precede the inspection. Grinding takes 7 units of time, polishing takes 10 units of time, weighting takes 1 unit of time for an unpolished product and 3 units of time for a polished one, and inspection takes 2 units of time for an unweighed product and 3 units of time for a weighed one. What is the fastest production schedule?

Solution

Schedule 1 is the fastest

Schedule 1 7 units 1 units 10 min 3 units 21 units
Grinding Weighing Polishing Inspection Total
Schedule 2 7 units 10 units 2 units 3 units 22 units
Grinding Polishing Inspection Weighing Total