A critical activity is an activity where the slack time is A

A critical activity is an activity where the slack time is

A. Positive
B. Negative
C. Zero
D. Loose
A critical activity is an activity where the slack time is

A. Positive
B. Negative
C. Zero
D. Loose

A. Positive
B. Negative
C. Zero
D. Loose

Solution

option C is zero

in the critical path activities, the slack time between earliest starting time and latest finishing time is zero. if the activities have slack time more than zero, then it should not be called as critical path.