A project is showed as follows a Find out the critical path
A project is showed as follows: (a) Find out the critical path of the Project (b) Fin out the duration of the projcet (c) Find out the slack time for each activity
Solution
a) critical path:
1. A-D-G = 8+5+7 =20 days
2. A-E-I =8+1+9 =18 days
3. B-I = 4+9 =13 days
4. C-F-I = 3+2+9 = 14 days
5. C-H-J = 3+6+9= 18 days
Critical path = A-D-G being the longest
b. Duration = 20 days (duration of the critical path)
c. Slack time:
| Task Name | Duration (exp. time) | ES | EF | LS | LF | Slack |
| Start | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Task A | 8.00 | 0.00 | 8.00 | 0.00 | 8.00 | 0.00 |
| Task B | 4.00 | 0.00 | 4.00 | 7.00 | 11.00 | 7.00 |
| Task C | 3.00 | 0.00 | 3.00 | 5.00 | 8.00 | 5.00 |
| Task D | 5.00 | 8.00 | 13.00 | 8.00 | 13.00 | 0.00 |
| Task E | 1.00 | 8.00 | 9.00 | 10.00 | 11.00 | 2.00 |
| Task F | 2.00 | 3.00 | 5.00 | 9.00 | 11.00 | 6.00 |
| Task G | 7.00 | 13.00 | 20.00 | 13.00 | 20.00 | 0.00 |
| Task H | 6.00 | 3.00 | 9.00 | 8.00 | 14.00 | 5.00 |
| Task I | 9.00 | 9.00 | 18.00 | 11.00 | 20.00 | 2.00 |
| Task J | 6.00 | 9.00 | 15.00 | 14.00 | 20.00 | 5.00 |
| Finish | 0.00 | 20.00 | 20.00 | 20.00 | 20.00 | 0.00 |