What is the theoretical minimum number of workstations Round





What is the theoretical minimum number of workstations? (Round your answer to the next whole number.)








rev: 08_07_2014_QC_52260

An assembly line is to be designed to operate 12 hours per day and supply a steady demand of 450 units per day. Here are the tasks and their performance times:

Solution

b. work station time is= 205 seconds

total working time is= 12*60*60= 43200 seconds

43200/450= 96 seconds per unit

c. minimum number of work stations= 5

d. the work stations are= ADGJL

e. they are using efficiency of = 96/205= 48%

f. then the output should be increased