Q1 Consider a process consisting of three activities Activit
Q1. Consider a process consisting of three activities:
Activity
Processing Time (Min./Unit)
1
2
3
60
30
40
What is the bottleneck? How much is the process capacity? How many units can be produced in a 24-hour day?
Suppose we have added extra machines to each activity as follows:
Activity
Processing Time (Min./Unit)
Number of Machines
1
2
3
60
30
40
3
2
2
What is the bottleneck now? How much is the process capacity? How many units can be produced in a 24-hour day?
| Activity | Processing Time (Min./Unit) |
| 1 2 3 | 60 30 40 |
Solution
Q1. The bottleneck is Activity 1 since it takes the most time among all activities.
Process capacity is the capacity of bottleneck process, Activity 1 processing time is 60 mins/unit, and hence process capacity is 1/hr or 24/day
The first unit will take 130 mins to complete, rest after that units will be produced at 60mins each. Thus production in a day = ((24*60) – 130)/60 +1 = approx. 22 units
Q2. Since we are adding machines effective processing time decreases
Activity 1 = 60/3 = 20 mins
Activity 2 = 30/2 = 15 mins
Activity 3 = 40/2 = 20 mins
Thus here bottleneck is activity that has highest processing time i.e. activity 1 and activity 2
Processing capacity = 60/20 = 3 per hour or 72 per day
Q1. The bottleneck is Activity 1 since it takes the most time among all activities.
Process capacity is the capacity of bottleneck process, Activity 1 processing time is 60 mins/unit, and hence process capacity is 1/hr or 24/day
The first unit will take 130 mins to complete, rest after that units will be produced at 60mins each. Thus production in a day = ((24*60) – 130)/60 +1 = approx. 22 units
Q2. Since we are adding machines effective processing time decreases
Activity 1 = 60/3 = 20 mins
Activity 2 = 30/2 = 15 mins
Activity 3 = 40/2 = 20 mins
Thus here bottleneck is activity that has highest processing time i.e. activity 1 and activity 2
Processing capacity = 60/20 = 3 per hour or 72 per day
Q1. The bottleneck is Activity 1 since it takes the most time among all activities.
Process capacity is the capacity of bottleneck process, Activity 1 processing time is 60 mins/unit, and hence process capacity is 1/hr or 24/day
The first unit will take 130 mins to complete, rest after that units will be produced at 60mins each. Thus production in a day = ((24*60) – 130)/60 +1 = approx. 22 units
Q2. Since we are adding machines effective processing time decreases
Activity 1 = 60/3 = 20 mins
Activity 2 = 30/2 = 15 mins
Activity 3 = 40/2 = 20 mins
Thus here bottleneck is activity that has highest processing time i.e. activity 1 and activity 2
Processing capacity = 60/20 = 3 per hour or 72 per day