A machine cell uses 300 pounds of a certain material each da

A machine cell uses 300 pounds of a certain material each day. Material is transported in vats that hold 19 pounds each. Cycle time for the vats is about two hours. The manager has assigned an inefficiency factor of .04 to the cell. The plant operates on an eight-hour day.



A machine cell uses 300 pounds of a certain material each day. Material is transported in vats that hold 19 pounds each. Cycle time for the vats is about two hours. The manager has assigned an inefficiency factor of .04 to the cell. The plant operates on an eight-hour day.

Solution

efficiency factor=0.96

material in each vat=19 pound
material taken by machine from each vet =19*0.96 = 18.24 pounds

machine requires 300 pound material

so,number of vats required =300 /18.24 =16.45 =17

hence 17 vats required