When discussing the BCP, critical resources are usually divided into five primary categories. The categories are which of the following groups?

A. Business, administrative, user, technical, and data

B. Administrative, policy, user, technical, and data

C. Business, facility and supply, user, technical, and nontechnical

D. Business, facility and supply, user, technical, and data

Solution

D. Business, facility and supply, user, technical, and data are the five primary categories. Answers A, B, and C are incorrect because they do not describe the five categories.