If earned duration is lower than current project day the pro
If earned duration is lower than current project day, the project is O Delayed O On plan Ahead of schedule
Solution
In the initial stage we will the project and project should be completed within the duration of the project. According to above data If earned duration is lower than current project day, the project is Ahead of schedule