If earned duration is lower than current project day the pro

If earned duration is lower than current project day, the project is O Delayed O On plan Ahead of schedule

Solution

In the initial stage we will the project and project should be completed within the duration of the project. According to above data If earned duration is lower than current project day, the project is Ahead of schedule

 If earned duration is lower than current project day, the project is O Delayed O On plan Ahead of schedule SolutionIn the initial stage we will the project and