1. [Question 5.2 in Cachon, Terwiesch 2013] Consider the dependency matrix and the activity durations (in days) provided below.
a. What is the critical path?
b. What is the earliest time that the project can be completed?
Dependency Matrix 10 5 2 X 5 10 10 4 Activity: Time: 12 4 4Solution
the critical path is 1-3-4-6-7-9-10
b. the project can be completed in earliest time of 27 days
![1. [Question 5.2 in Cachon, Terwiesch 2013] Consider the dependency matrix and the activity durations (in days) provided below. a. What is the critical path? b. 1. [Question 5.2 in Cachon, Terwiesch 2013] Consider the dependency matrix and the activity durations (in days) provided below. a. What is the critical path? b.](/WebImages/4/1-question-52-in-cachon-terwiesch-2013-consider-the-dependen-978200-1761501937-0.webp)