With iterative techniques project progress can be measured m

With iterative techniques, project progress can be measured most effectively by: a. counting the number of team meetings held in a 4-8 week time frame b. counting lines of code that have been written c. looking at product backlog d. counting the number of interactions between team members and the customer

Solution

D.counting the number of interactions between team members and the customer

As this tells that there is some progress in project and new requirements are to come.

With iterative techniques, project progress can be measured most effectively by: a. counting the number of team meetings held in a 4-8 week time frame b. counti

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site