1 Compute the MIRR for Project Y and accept or reject the pr
1. Compute the MIRR for Project Y and accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 12 percent.
Time:
0
1
2
3
4
5
Cash flow:
?5,000
1,000
1,000
0
2,000
2,000
A. 7.62 PERCENT, ACCEPT
B. 7.62 PERCENT, REJECT
C. 47.09 PERCENT, ACCEPT
D. 47.09 PERCENT, REJECT
| Time: | 0 | 1 | 2 | 3 | 4 | 5 |
| Cash flow: | ?5,000 | 1,000 | 1,000 | 0 | 2,000 | 2,000 |
Solution
We use the formula:
A=P(1+r/100)^n
where
A=future value
P=present value
r=rate of interest
n=time period.
Hence future value of inflows=1000(1.12)^4+1000(1.12)^3+2000(1.12)+2000
=$7218.44736
MIRR=[Future value of inflows/Present value of outflows]^(1/time period)-1
[$7218.44736/5000]^(1/5)-1
=7.62%(Approx).
Hence since MIRR is less than the cost of capital;project must be rejected.(B).

