QUESTION 15construction finance GS construction is awarded a
QUESTION 15-construction finance:
GS construction is awarded a contract to build a commercial building. The contract price is $1,500,000 and during the first month of the job, the following transactions occurred:
Cash expenditures to date
$300,000
Total expenditures to date
$350,000
Estimated expenditure to complete
$1,100,000
Total estimated expenditures
$1,450,000
Billing to date
$280,000
Cash collected to date
$250,000
What is \"Revenue to Date\" in Cash Method?
50,000
250,000
280,000
300,000
Solution
Revenue to Date = Total expenditures to date - Cash expenditures to date
= $350,000 - $300,000
= $50,000