A task representing a general activity of construction that
A task representing a general activity of construction that contains multiple subtasks is considered which of the following?
Summary task
Milestone activity
Subtask
None of the above
Linking activity
The original schedule created at the beginning of the project against which the project\'s progress is measured is which of the following?
None of the above
Resource schedule
Updated schedule
Baseline schedule
Recovery schedule
| a. | Summary task | |
| b. | Milestone activity | |
| c. | Subtask | |
| d. | None of the above | |
| e. | Linking activity |
Solution
For general activity construction we use Mildstone chart and If construtions are new (probabilistic in nature) we use PERT Method. For first question anser is Mildstone Activity
The original schedule created at the begining of the project is Baseline Schedule