A task representing a general activity of construction that

A task representing a general activity of construction that contains multiple subtasks is considered which of the following?

Summary task

Milestone activity

Subtask

None of the above

Linking activity

The original schedule created at the beginning of the project against which the project\'s progress is measured is which of the following?

None of the above

Resource schedule

Updated schedule

Baseline schedule

Recovery schedule

a.

Summary task

b.

Milestone activity

c.

Subtask

d.

None of the above

e.

Linking activity

Solution

For general activity construction we use Mildstone chart and If construtions are new (probabilistic in nature) we use PERT Method. For first question anser is Mildstone Activity

The original schedule created at the begining of the project is Baseline Schedule