Assume you are riskaverse and have the following three choic
Assume you are risk-averse and have the following three choices.
Expected Standard
Value Deviation
A $ 2,010 $ 1,700
B 2,420 1340
C 2,180 1,490
Compute the coefficient of variation for each. (Round your answers to 3 decimal places.)
Coefficient of Variation
A _______
B_______
C_______
Which project will you select? Project A Project B or Project C ?
Solution
coefficient of variation=Standard deviation/Expected value
Hence since individual is risk averse;choice having lowest coefficient of variation must be selected ie Project B.
| coefficient of variation | |
| A | (1700/2010)=0.846 |
| B | (1340/2420)=0.554 |
| C | (1490/2180)=0.683(Approx). |