A building contractor is to dig a foundation 30 feet long 18
A building contractor is to dig a foundation 30 feet long, 18 feet wide, and 3 feet deep. The contractor pays $25 per load for trucks to remove the dirt. Each truck holds 6 cubic yards. What is the cost to the contractor to have all the dirt hauled away?
Solution
Given conditions
3 feet = 1 yard, therefore we have
Length = 30 feet = 10 yard
Width = 18 feet = 6 Yard
Depth = 3 feet = 1 Yard
the total volume excavated is 10*6*1 = 60 Yard3
Cost of removing 1 truck of dirt i.e 6 Cubic yards is $25
therefore for removing 60 cubic yards of dirt is $250.