Question 11 Which one of the following assumptions is genera
Solution
Q11 c) Risk and uncertainties are lowest in initial phase. This is the assumpltions, project managers does before the start of the project. Usually there is less risk in the initial stage of project.
Q12 a) Contract Management - The contract management consists of invitation to bid, bid evaluation, crontract implementation. It also includes contract relationship, addressing related problems, ebsuring both party meet each other\'s expectation.
Q13 b) Integration Management. Integration Management includes the process and activity needed to identify, define, combine, unifying and coordinating various process.
Q14 c) Scope baseline, Cost baseline and schedule baseline
Q15 b) Prviding cost/benefit analysis during the project selection process. The project manager is responsible for managing the budget and do not plan or analyse the benefit of the project, It is generally done by top level managers such as Owners, Directors, Investors etc.

