Marcus and Tony work for the same company. Marcus lays a slab of concrete in 3 hours. Tony lays the same size slab in 7 hours. If both work on the job and the cost of labor is$ 60.00 per hour, decide what the labor estimate should be.
Solution
Solution: - Marcus lays slab in 3hrs. So in one hr he works 1/3 job
In the same manner Tony works 1/7 job
in 1 hr total job = (1/3 +1/7) = 10/21
Hence to finish the job total hrs are required = 21/10 = 2.1 hr
Total cost for the work = 2.1 X 60 = $126
3 Marcus = 7 Tony
1 Marcus = 7/3 Tony
M + T = 126
7/3 T +T = 126
10 T/3 =126
T = $ 37.8
M = 126 - 37.8 = $88.2