0 0 Same Schedule Hand Drawn with Hand Calculations Solution
0 0 Same Schedule -Hand Drawn with Hand Calculations
Solution
This is the activity on node diagram and also in both the number one is representing normal time and one is representing total float.
Total float can be calculated after calculating latest finish time minus earliest finish time
You may also calculate same by calculating latest start time minus earliest start time.