This Question: 1 pt 8 of 31 (0 complete) This Test: 31 pts possil Question Help Suppose you\'re presented with a proposal for a project that costs $4,100 and will bring in $20.200 the first year. The next year, youll have to pay out S1 6,000, with a cost of capital of 12%, calculate the net present value (NPV) for this project. The NPV of the project is s (Round to the nearest cent.)

Solution

1.

Cash flow PVF @ 12% PV
Year 0 -4100 1.00 -4100
Year 1 20200 .8928 18034.56
Year 2 -16000 .7972 -12755.20
NPV 1179 (Rounded)