The output of the process is called the master schedule a M

The output of the ___ process is called the master schedule. a. MRP b. MPS c. MTO d. MPC

Solution

MPS is the right answer, MPS means master production schedule

MRP means material requirement planning, it is a procurement related process.

MTO means Make to Order, which is a type of manufacturing where the process starts only after the order is given by the customer.

MPC means Manufacturing production control. this happens during the production. but the production shedule should have made before starting the production

The output of the ___ process is called the master schedule. a. MRP b. MPS c. MTO d. MPCSolutionMPS is the right answer, MPS means master production schedule MR