Complete the following MRP matrix for Item X Determine when

Complete the following MRP matrix for Item X. Determine when orders should be released and the size of those orders.

Item: X

LLC: 0

Period

Lot Size: Min 50

LT: 2

1

2

3

4

5

6

7

8

Gross Requirements

25

30

56

25

100

40

30

20

Scheduled Receipts

50

Projected on Hand

30

Net Requirements

Planned Order Receipts

Planned Order Releases

Release orders in periods 1 through 5 for quantities of 50, 50, 56, 50, and 50 respectively.

Item: X

LLC: 0

Period

Lot Size: Min 50

LT: 2

1

2

3

4

5

6

7

8

Gross Requirements

25

30

56

25

100

40

30

20

Scheduled Receipts

50

Projected on Hand

30

Net Requirements

Planned Order Receipts

Planned Order Releases

Solution

Ans:

The MRP matrix for the item x is given below:

Item: X LLC: 0 Period
Lot Size: Min 50 LT: 2 1 2 3 4 5 6 7 8
Gross Requirements 25 30 56 25 100 40 30 20
Scheduled Receipts 50
Projected on Hand 30 5 25 25 19 44 0 10
Net Requirements 31 6 56 40 20
Planned Order Receipts 50 50 56 50 50
Planned Order Releases 50 50 56 50 50
Complete the following MRP matrix for Item X. Determine when orders should be released and the size of those orders. Item: X LLC: 0 Period Lot Size: Min 50 LT:
Complete the following MRP matrix for Item X. Determine when orders should be released and the size of those orders. Item: X LLC: 0 Period Lot Size: Min 50 LT:

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site