QUESTION 10 Dehner Corporation uses a joborder costing syste

QUESTION 10 Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct company based its predetermined overhead rate for the current year on the following data: labor-hours. The Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour 40,000 $96,000 $3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 $ 755 $4,000 The estimated total manufacturing overhead is closest to: O$96,003 $120,000 Click Save and Submit to save and submit. Click Save All Answers to save all answers. Save Al A

Solution

Answer D. $216,000 Fixed MOH      96,000.00 Variable MOH - 40,000 DLh X $3    120,000.00 Total Estimated MOH    216,000.00
 QUESTION 10 Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct company based its predetermi

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site