When implementing a packaged Enterprise Resource PlanningERP
Solution
a)
This is a paired t test.
*********
b)
Let ud = u(after) - u(before)
 .              
 Formulating the null and alternative hypotheses,              
               
 Ho:   ud   >=   0  
 Ha:   ud   <   0   [ANSWER]
***************
c)
Calculating the mean of the differences,
               
 XD =    -0.9625       [ANSWER]
***********
d)
Calculating the standard deviation of the differences (third column):              
               
 s =    0.980221064          
               
 Thus, the standard error of the difference is sD = s/sqrt(n):              
               
 sD =    0.346560481          
**************
f)
As df = n - 1 = 7 [ANSWER]
*************
g)
 As we can see, this is a    left   tailed test, as Ha used <, at least in our convention here.
***************
h)                      
               
               
 As t = [XD - uD]/sD, where uD = the hypothesized difference =    0   , then      
               
 t =    -2.77729301          
               
               
               
 Thus, using p values, as this is left tailed,              
               
 p =        0.013702409   [ANSWER]
****************
i)  
               
 As P < 0.05, WE REJECT THE NULL HYPOTHESIS.      
There is significant evidence that the average time to financial close is less after the implementation of their ERP system. [CONCLUSION]  
               
               
               
![When implementing a packaged Enterprise Resource Planning[ERP] system, many companies report that the module they first install is Financial Accounting. Among   When implementing a packaged Enterprise Resource Planning[ERP] system, many companies report that the module they first install is Financial Accounting. Among](/WebImages/7/when-implementing-a-packaged-enterprise-resource-planningerp-990305-1761509148-0.webp)
![When implementing a packaged Enterprise Resource Planning[ERP] system, many companies report that the module they first install is Financial Accounting. Among   When implementing a packaged Enterprise Resource Planning[ERP] system, many companies report that the module they first install is Financial Accounting. Among](/WebImages/7/when-implementing-a-packaged-enterprise-resource-planningerp-990305-1761509148-1.webp)