Question 3 A Project consists of the following activities Ac
Question 3
A Project consists of the following activities. Activities Times are given in weeks.
Activity
Immediate Predecessors
Optimistic
Most Likely
Pessimistic
A
--
13
16
19
B
A
21
37
33
C
A
5
7
15
D
A
7
9
13
E
B
24
28
32
F
B
15
18
25
G
C, F
19
21
27
H
D
24
28
32
I
H
5
9
18
J
G, I
4
12
13
K
E, J
15
19
24
 1. Use appropriate nodes and arrows to draw the network diagram. On the network diagram, label the activity time under each node.
 2. Scan your network diagram in the .pdf file format.
 3. Submit your assignment by uploading the file.
| Activity | Immediate Predecessors | Optimistic | Most Likely | Pessimistic | 
| A | -- | 13 | 16 | 19 | 
| B | A | 21 | 37 | 33 | 
| C | A | 5 | 7 | 15 | 
| D | A | 7 | 9 | 13 | 
| E | B | 24 | 28 | 32 | 
| F | B | 15 | 18 | 25 | 
| G | C, F | 19 | 21 | 27 | 
| H | D | 24 | 28 | 32 | 
| I | H | 5 | 9 | 18 | 
| J | G, I | 4 | 12 | 13 | 
| K | E, J | 15 | 19 | 24 | 
Solution