1.      Compute the NPV statistic for Project Y given the following cash flows and if the appropriate cost of capital is 12 percent.

Project Y

Time

0

1

2

3

4

5

Cash Flow

–$

10,000

$

3,000

$

4,000

$

1,000

$

2,000

$

500

A.      18,133.88

B.       -1,366.99

C.       -1,539.14

D.      -1,866.12

Time

0

1

2

3

4

5

Cash Flow

–$

10,000

$

3,000

$

4,000

$

1,000

$

2,000

$

500

Solution

The Net Present Value [NPV] of the Project Y is “D. - $1,866.12”

Net Present Value [NPV] = Present Value of Annual cash flows – Initial Investment

= [$3,000 / (1.12)1] + [$4,000 / (1.12)2] + [$1,000 / (1.12)3] + [$2,000 / (1.12)4] + [$5,000 / (1.12)5] - $10,000

= [$2,678.57 + 3,188.78 + 711.78 + 1,271.04 + 283.71] - 10,000

= $8,133.88 – 10,000

= -$1,866.12 [Negative NPV]

1. Compute the NPV statistic for Project Y given the following cash flows and if the appropriate cost of capital is 12 percent. Project Y Time 0 1 2 3 4 5 Cash
1. Compute the NPV statistic for Project Y given the following cash flows and if the appropriate cost of capital is 12 percent. Project Y Time 0 1 2 3 4 5 Cash

Get Help Now

Submit a Take Down Notice

Tutor
Tutor: Dr Jack
Most rated tutor on our site