Young bulls contracting repaved 50 miles of twolane roadway

Young bulls contracting repaved 50 miles of two-lane roadway with a crew of six employees. The crew worked eight days and used $7000 worth of paving materials. Nearby little dog construction repaved 30 miles of four-lane roadway working ten days with a crew of five people using $9000 of paving material. Both young bull and little dog rented the same paving equipment to complete their respective products costing each $1500 per day.

Young bull\'s labor productivity_________________ = single lane miles/ day (one decimal place)

little dog\'s labor productivity___________________ = single lane miles/day

Young bull\'s labor productivity =

Solution

young bulls build 50 miles two lane road, it can be consider as 100 miles of single lane

the productivity= 100/64= 1.5625miles per day

little dogs productivity= 30*4= 120 miles single lanes/per one labor

the productivity= 120/50= 2.4 miles single lane per day/one labor

Young bulls contracting repaved 50 miles of two-lane roadway with a crew of six employees. The crew worked eight days and used $7000 worth of paving materials.