C contracted with a private owner O to build a fivestory com

C contracted with a private owner, O, to build a five-story commercial building under a changes clause allowing changes in \"the general scope of the work.\"

Must C perform the work to do any of the following orders: a. add an underground garage; b. build a hot tub in the pool area on the roof; c. substitute toilets with a lower water tank capacity for those designated; d. half-way through finishing the fourth floor, delete all the interior improvements on the fourth floor down to the structural members? In each case, how should the change in price be determined?

The order of presentation in a case brief is not random, in fact it generally follows this order of presentation:

Introduction.

Facts: Those events that cause a legal dispute.

Issues: Unsettled legal principle about which the parties disagree.

Rules: The legal rules of law that apply to this case.

Application: The Analysis

Conclusion: Final Ruling and Disposition

Solution

As the contractor must have recieved the previous quotation for the work,since the changes has to be performed in the previous,it shall be done by taking care the needs of the private owner. Now,the changes can be made by comparing the present need and the previous requirements of the project. The changes in prices can be evaluated by estimating the price of the new requirements(which is estimated according the market price of various products).

C contracted with a private owner, O, to build a five-story commercial building under a changes clause allowing changes in \