The following information is provided about Job 5 Actual dir
The following information is provided about Job #5:
Actual direct material costs, $10,000
 Actual direct labor costs, $20,000
 Actual overhead costs, $15,000
 Estimated direct material costs, $12,000
 Estimated direct labor costs, $19,000
 Estimated (applied) overhead, $18,000
Assuming the company uses NORMAL costing instead of actual costing, what is the cost of Job #5?
$45,000
$48,000
$49,000
$50,000
Solution
Calculate cost of job #5:
so answer is c) $49000
| Material cost | 12000 | 
| Labour cost | 19000 | 
| Overhead applied | 18000 | 
| Total cost of job 5 | 49000 | 