A saturated power cycle uses steam at 1100 psia and a conden
     A saturated power cycle uses steam at 1100 psia and a condenser pressure of 10 psia. This power plant requires annual turbine maintenance that lasts at least 3 weeks. Federal regulation have limited the thermal power to 85% of its full value the  efficiency of the plant is  0.991  0.794  0.743  0.670  0.653  0.673  0.438  0.257 
  
  Solution
A year has 52 weeks.
Shutdown period = 3 weeks
shutdown time = 3/52 = 0.0577
Actual run time = 1 - 0.0577 = 0.9423
85% of 0.9423 = 0.801
Hence, max. capacity factor = 0.801 Option d is correct.