M410 Assigning Costs Using Activity Proportions LO 45 Estima
M4-10 Assigning Costs Using Activity Proportions [LO 4-5 Estimated 108,800 (Round your final answers to the nearest whole number.)
Solution
Estimated Total Cost (Given) Activities (given) Actvities Rate Machining 366600 13000 28.20 Setup 69825 350 199.50 Quality Control 108800 800 136.00 Activities (given) Activities Rate Overhead Assigned Machining 4680 28.20 131976 Setup 70 199.50 13965 Quality Control 208 136.00 28288 Total Overhead 174229