12 Use the following data to find the direct labor cost vari
12. Use the following data to find the direct labor cost variance. $7/hr.) $28 per unit Direct labor standard (4 hrs. Actual hours worked per unit Actual units produced Actual rate per hour 3.5 hours 3,500 units $7.50 A. $6,125 unfavorable. B. $7,000 unfavorable. $7,000 favorable. 12,250 favorable. ,86,125 favorable.
Solution
Since two unrelated questions are posted, the first appearing question is answered below;
1. Direct labour cost variance = (standard time* standard rate) - (actual time* actual rate)
here,
Standard time = standard time per unit * number of units produced
=> 4hrs * 3,500 units =>14,000 hours.
Standard rate = $7 per hour
Actual time = actual hours per unit * number of units
=>3.5 hours * 3,500
=>12,250 hours.
Actual rate =$7.50
Direct labour cost variance = (14,000*$7) - (12,250*$7.5)
=>$98,000 - $91,875.
=>$6,125 favourable...(since actual cost is less than standard, we have favourable balance).
