NPV Project L costs 60000 its expected cash inflows are 1300
Solution
NPV = $10885.53
--------------------------------------------------------------------------------------------------------------------------
NPV is the difference between the present value of all cash inflow and the initial cost of an asset or project.
All the future cash flows are discounted using discounting rate or required rate and the sum of all the discounted cash flows will be subtracted with the initial cost.
NPV = PV of future cash inflow - initial cost
Pls refer below table for NPV calculation,
Year
cash inflow
PV factor @ 14%
PV of cash flow
1
13000
0.87719298
11403.51
2
13000
0.76946753
10003.08
3
13000
0.67497152
8774.63
4
13000
0.59208028
7697.04
5
13000
0.51936866
6751.79
6
13000
0.45558655
5922.63
7
13000
0.39963732
5195.29
8
13000
0.35055905
4557.27
9
13000
0.30750794
3997.60
10
13000
0.26974381
3506.67
11
13000
0.23661738
3076.03
Total
70885.53
Initial cost
60000
NPV
10885.53
--------------------------------------------------------------------------------------------------------------------------
Feel free to comment if you need further assistance J
Pls rate this answer if you found it useful.
| Year | cash inflow | PV factor @ 14% | PV of cash flow |
| 1 | 13000 | 0.87719298 | 11403.51 |
| 2 | 13000 | 0.76946753 | 10003.08 |
| 3 | 13000 | 0.67497152 | 8774.63 |
| 4 | 13000 | 0.59208028 | 7697.04 |
| 5 | 13000 | 0.51936866 | 6751.79 |
| 6 | 13000 | 0.45558655 | 5922.63 |
| 7 | 13000 | 0.39963732 | 5195.29 |
| 8 | 13000 | 0.35055905 | 4557.27 |
| 9 | 13000 | 0.30750794 | 3997.60 |
| 10 | 13000 | 0.26974381 | 3506.67 |
| 11 | 13000 | 0.23661738 | 3076.03 |
| Total | 70885.53 | ||
| Initial cost | 60000 | ||
| NPV | 10885.53 |


